Public hearings on the reconstruction of a cryogenic installation for deep processing of dry stripped gas DSG with the yield of new products were just another stage of the project implementation, which took place on September 30 at the premises of the Almetyevsk Municipal District Executive Committee.

The implementation of the proposed technical solutions will allow optimizing technological processes, increasing the productivity of the cryogenic installation for deep processing of dry stripped gas to obtain new products, the depth of ethane fraction recovery, as well as increasing the calorific value of CO2 and contributing to environmental protection by reducing the amount of hydrocarbons in the nitrogen-containing gas.
Thanks to modern technologies, MGPZ will reduce the amount of hydrocarbon emissions into the atmosphere by approximately 42 .

The plans provide that the reconstructed cryogenic installation will be is located within the industrial site of the operating Minnibayevo gas processing plant and processes dry stripped gas produced by the MGPZ. The planned renovation will expand the existing installation by constructing a new unit and connecting it to the utility networks.

The commissioning of the new installation is scheduled for December 2023.
2 октября
Crude Oil Production Enterprises of the TATNEFT Group of Companies produced 2,104 thousand tonnes of crude oil in September with the production volume from the beginning of the year amounting to 19,548 thousand tonnes, which was 2,803.7 thousand tonnes less than during the same period in 2019. PJSC TATNEFT s production volume amounted to 2,078 thousand tonnes of crude oil in September with the Company s production from the beginning of the year amounting 19,307 thousand tonnes (-2,799 thousand tonnes versus the relevant period in 2019).